Your site is mapped as bush fire prone land; you need a BAL certificate before the Complying Development Certificate (CDC) can be issued. Until that certificate has been issued, the approval can’t be finalised by the certifier, and the intention of the CDC process as a fast-tracked assessment pathway is not effectively utilised.
We prepare BAL certificates for builders and owner-builders across NSW. Every certificate is prepared personally by our principal consultant, Jonathan Hardy. Jonathan is a BPAD accredited bushfire practitioner with FPA Australia (#50394) and holds a Graduate Diploma in Bush Fire Protection from Western Sydney University. He also contracts his time with the newly established Development Coordination Authority in the review of bush fire prone development in NSW.
This page covers what a BAL certificate in NSW involves, who can issue one, where it sits in your approval, what it means for sheds and Class 10 structures, and what to send us so nothing holds your certificate up.
On this page
What a BAL certificate is, and who can issue one
A Bush Fire Attack Level certificate, the BAL certificate for short, states the BAL rating for proposed bush fire prone development and is assessed under the provisions of Planning for Bush Fire Protection 2019. The factors assessed in the process are vegetation type, effective slope, and distance from the classified vegetation to the building. It’s prepared to meet the submission requirements for development on bush fire prone land, providing your certifier with the certification required under Section 1.19A of the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008.
Depending on the council, you’ll sometimes hear the same document called a FALRA Certificate (Newcastle) or a Bush Fire Attack Level Risk Assessment Certificate (Wollongong, Central Coast). And builders and certifiers use their own shorthand for it too: a BAL assessment, a BAL report, a BAL rating. Same document, different names.
When a certifier asks for a BAL certificate prepared by a suitably qualified consultant, the accreditation scheme they are referring to is the Bushfire Planning and Design (BPAD) scheme facilitated by Fire Protection Association (FPA) Australia. We hold adequate BPAD accreditation for all applications made under the CDC approval pathway.

If you want further information on how BAL ratings are worked out, refer to our BAL ratings explainer.
Complying development on bush fire prone land
A CDC is the fast-track approval under the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008. Meet the pre-set standards and a registered certifier, private or council, can approve the build without a development application. For builders there is significant appeal: shorter approvals, earlier starts, faster finishes.
To utilise the CDC approval pathway, the BAL has to come in low enough: complying development generally is not available where a proposed development is assessed as BAL 40 or Flame Zone.
If a site does assess that high, the pathway changes, not the job. Instead of a BAL certificate, a full bushfire assessment report is required to accompany the documentation for a development application.
For the wider picture on approvals and requirements, see our guide to building in bush fire prone areas in NSW.
Where the certificate fits in your CDC timeline
The order of operations that keeps a job moving:
- Check the map first. The NSW RFS bush fire prone land tool or your council’s map shows whether the lot is affected, before anything is designed or priced. Or send us the address and we’ll check it for you, no charge.
- Get the assessment done early. The BAL certificate for building approval has to be issued before the CDC can be issued, and having the rating confirmed up front means the design and the materials pricing are built on the real number, not a guess.
- Certificate goes to your certifier. They issue the CDC with the rating attached.
- Build to the standard. The rating identifies the relevant sections of AS 3959-2018 that apply to the construction standards.
What you need to supply
1. The site plan
A site plan provides the details of the existing and proposed development. For a BAL Certificate it must show:
- Scale and dimensions. Drawn to a stated scale, 1:200 is standard for residential lots, dimensioned in metres or millimetres, and legible. The drawing must be identifiable, lot, DP and street at minimum, a plan reference and date where it carries one, because the certificate cites the exact plan it was assessed against. Separation distances are measured off this plan, so an unscaled sketch makes accurate assessment of the most suitable BAL rating difficult.
- The proposed works, positioned on the lot. The full footprint of the new dwelling, shed, garage or carport, or the extent of the alterations and additions. The BAL relates to the building in its assessed position. If the footprint moves after assessment, the certificate no longer accurately reflects the proposed development.
- Boundary setbacks. Setbacks from the proposed works to the site boundaries, including separation from new work to existing structures on the site.
- Existing structures, and any demolition. Everything existing on the site and anything proposed for demolition.
- Identification and orientation. Lot and DP, street address, and a north point. The method assesses each compass direction separately and the highest result governs the building, so the plan must be orientated.
The reference example for this page: scale 1:200, dimensioned in millimetres, the proposed garage positioned by a tie to the existing dwelling and a setback to the side boundary, with lot, DP, site area and a north point. It meets every requirement above. Vegetation does not appear on a site plan; measuring separation to the hazard is part of the assessment.
2. A description of the development
State what the structure is and what it will be used for: a new dwelling, a secondary dwelling (granny flat) or guest accommodation, a shed for domestic garaging or storage, a shed for commercial or agricultural use, or alterations and additions with the extent of the new work.
An accurate description is how the job is scoped quickly and correctly at quotation, and how the certificate matches what your certifier approves.
3. Alterations and additions
The plan must distinguish the existing building from the new work. Where floor plans or elevations exist, provide them: the certificate has to identify which part of the building it covers.
What you don’t need to supply
Vegetation classification, slope measurement, the Fire Danger Index and separation distances. Producing those is the assessment, performed under PBP 2019 Appendix 1. Ground levels and contours are also not required, although some council application forms ask for them: slope is derived from mapping, and verified on site where an inspection is needed.
BAL rated sheds, garages and carports (Class 10)
Builders ask us about BAL rated sheds more than almost anything else. Class 10 structures, sheds, garages, carports, still trigger the certificate requirement when the land is mapped as bush fire prone and the job runs through the CDC pathway.
Two things worth knowing before you request a BAL certificate for a shed, garage or carport, a Class 10 building under the National Construction Code. A detached shed is assessed on its merits when the structure is within 6 metres of a habitable building, and is issued with a suitable BAL. Where a proposed Class 10a building is separated by more than 6 metres from a habitable building, bush fire protection building controls are not relevant, and a BAL certificate is not required. An attached garage or carport is also assessed on its merits. Further information is provided in our construction requirements guide.

Alterations and additions on bush fire prone land
Extensions and alterations on bush fire prone land can run through complying development too, and the certifier will want the BAL confirmed the same as for a new build. The rating applies to the new work. If you’re pricing a reno in a mapped area, get the rating before you lock in the design, not afterwards, when there could be implications for the viability of the project.
Turnaround and getting started
Allow around 5 business days from when we have everything listed under what you need to supply.
Most BAL certificates are completed from your site plan and current aerial imagery. If a site does need inspecting in person, we’ll tell you before we quote.
Call 0426 440 012 or send the site details through the contact page and you’ll get a fixed price quote and a timeframe. For more detail, see our BAL assessment service and our NSW BAL rating guide.
Common questions
Do you need a BAL rating certificate for complying development?
If the land is mapped as bush fire prone, yes. The certifier can’t issue the CDC without the rating confirmed.
Is a bushfire attack level certificate the same as a BAL certificate?
Yes. The full name is Bush Fire Attack Level certificate; BAL certificate is the everyday shorthand. Councils sometimes use their own names on top, like the FALRA Certificate in Newcastle. Same document, same assessment.
Bushfire report or BAL certificate, which one do I need?
For the CDC pathway, you need the BAL certificate. A full bushfire assessment report is the bigger document that supports a development application. If your job can’t meet the complying development standards, that’s usually the route it takes, and it’s work we handle as well. Our guide to the Bush Fire Assessment Report for a DA in NSW covers that pathway.
Do you need a bushfire risk assessment for a shed?
Only if it’s within 6 metres of a habitable building. Further away than that, bush fire building controls don’t apply and a BAL certificate isn’t required. Within 6 metres, it’s assessed on its merits like any other building.
What about a granny flat?
Secondary dwellings on bush fire prone land follow the same logic: certificate for the CDC where the pathway is available, and the rating drives the construction standard.
Buying a block and want the rating before you commit?
Smart move. A pre-purchase assessment tells you what the rating means for build cost before you’re locked in. Our guide to buying a house in a bush fire prone area covers what to check.
My land came back BAL 12.5. Do I still need the certificate?
Yes. A low rating still has to be documented for the certifier. The good news is the construction requirements at BAL 12.5 are the lightest tier.
How much does a BAL certificate cost?
Fixed price, quoted up front once we’ve seen the site details. Send them through or call 0426 440 012.